— Project Summary

Queue ID
PacifiCorp-C4-086
Capacity
450 MW
Technology
Solar
Status
active
Location
Emery, UT
Region
West
Developer
IA Status

BetaActiveSolarPacifiCorpLBNL

450 MW generation in Emery, UT · In queue since May 2024 · Proposed COD May 2029

450 MW

Capacity

1

Components

Solar

1y 10m

In Queue

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

5 years

Pre-Study0%
Queue EntryMay 15, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-05-31

Project Details

State

UT

County

Emery

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Camp Williams - Emery transmission line

Data Source

LBNL

No news available for this project.