BetaActiveSolarPacifiCorpLBNL
100 MW generation in Power, ID · In queue since May 2024 · Proposed COD December 2029
100 MW
Capacity
1
Components
Solar
1y 10m
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
5y 7m
Pre-Study0%
Queue EntryMay 15, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-12-31
Project Details
State
ID
County
Power
Region
West
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
American Falls Malad transmission line
Data Source
LBNL
No news available for this project.