BetaActiveSolarBatteryPacifiCorpLBNL
19.9 MW hybrid in Deschutes, OR · In queue since May 2024 · Proposed COD December 2028
19.9 MW
Capacity
1
Components
Solar
1y 10m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 7m
Pre-Study0%
Queue EntryMay 15, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-31
Project Details
State
OR
County
Deschutes
Region
West
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Penstock substation
Data Source
LBNL
No news available for this project.