— Project Summary

Queue ID
PacifiCorp-C4-043
Capacity
300 MW
Technology
Solar+Battery
Status
active
Location
Sanpete, UT
Region
West
Developer
IA Status

BetaActiveSolarBatteryPacifiCorpLBNL

300 MW hybrid in Sanpete, UT · In queue since May 2024 · Proposed COD January 2029

300 MW

Capacity

1

Components

Solar

1y 10m

In Queue

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

4y 8m

Pre-Study0%
Queue EntryMay 15, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-01-12

Project Details

State

UT

County

Sanpete

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Clover - Sigurd #2 transmission line

Data Source

LBNL