— Project Summary

Queue ID
PacifiCorp-C4-039
Capacity
300 MW
Technology
Solar+Battery
Status
active
Location
Franklin, ID
Region
West
Developer
IA Status

BetaActiveSolarBatteryPacifiCorpLBNL

300 MW hybrid in Franklin, ID · In queue since May 2024 · Proposed COD June 2028

300 MW

Capacity

1

Components

Solar

1y 10m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 1m

Pre-Study0%
Queue EntryMay 15, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-06-30

Project Details

State

ID

County

Franklin

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Treasureton substation

Data Source

LBNL