310.2 MW generation in Carbon, WY · In queue since May 2024 · Proposed COD July 2031
310.2 MW
Capacity
1
Components
Wind
1y 10m
In Queue
—
IA Status
COD target: 2031
Interconnection Timeline
Total Duration
7y 2m
Pre-Study0%
Queue EntryMay 14, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2031-07-01
Project Details
State
WY
County
Carbon
Region
West
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Heward substation
Data Source
LBNL