199.9 MW generation in Millard, UT · In queue since May 2024 · Proposed COD April 2029
199.9 MW
Capacity
1
Components
Gas
1y 10m
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 11m
Pre-Study0%
Queue EntryMay 13, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-04-01
Project Details
State
UT
County
Millard
Region
West
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Pavant substation
Data Source
LBNL
No news available for this project.