— Project Summary

Queue ID
PacifiCorp-C4-030
Capacity
400 MW
Technology
Gas
Status
active
Location
Power, ID
Region
West
Developer
IA Status

BetaActiveGasPacifiCorpLBNL

400 MW generation in Power, ID · In queue since May 2024 · Proposed COD October 2030

400 MW

Capacity

1

Components

Gas

1y 10m

In Queue

IA Status

COD target: 2030

Interconnection Timeline

Total Duration

6y 5m

Pre-Study0%
Queue EntryMay 13, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-10-01

Project Details

State

ID

County

Power

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Borah Populus transmission line

Data Source

LBNL