150 MW storage in Duchesne, UT · In queue since May 2024 · Proposed COD January 2029
150 MW
Capacity
1
Components
Battery
1y 10m
In Queue
—
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
4y 8m
Pre-Study0%
Queue EntryMay 10, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-01-07
Project Details
State
UT
County
Duchesne
Region
West
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Carbon - Ashley Valley tranmission line
Data Source
LBNL