— Project Summary

Queue ID
PacifiCorp-C4-024
Capacity
150 MW
Technology
Battery
Status
active
Location
Duchesne, UT
Region
West
Developer
IA Status

BetaActiveBatteryPacifiCorpLBNL

150 MW storage in Duchesne, UT · In queue since May 2024 · Proposed COD January 2029

150 MW

Capacity

1

Components

Battery

1y 10m

In Queue

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

4y 8m

Pre-Study0%
Queue EntryMay 10, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-01-07

Project Details

State

UT

County

Duchesne

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Carbon - Ashley Valley tranmission line

Data Source

LBNL

No news available for this project.