— Project Summary

Queue ID
PacifiCorp-C4-022
Capacity
500 MW
Technology
Battery
Status
active
Location
Salt Lake, UT
Region
West
Developer
IA Status

BetaActiveBatteryPacifiCorpLBNL

500 MW storage in Salt Lake, UT · In queue since May 2024 · Proposed COD December 2029

500 MW

Capacity

1

Components

Battery

1y 10m

In Queue

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

5y 7m

Pre-Study0%
Queue EntryMay 8, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-12-31

Project Details

State

UT

County

Salt Lake

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Oquirrh substation

Data Source

LBNL

No news available for this project.