— Project Summary

Queue ID
PacifiCorp-C4-020
Capacity
402 MW
Technology
Wind
Status
active
Location
San Juan, UT
Region
West
Developer
IA Status

BetaActiveWindPacifiCorpLBNL

402 MW generation in San Juan, UT · In queue since May 2024 · Proposed COD June 2028

402 MW

Capacity

1

Components

Wind

1y 10m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 1m

Pre-Study0%
Queue EntryMay 8, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-06-01

Project Details

State

UT

County

San Juan

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Huntington - Pinto transmission line

Data Source

LBNL

No news available for this project.