BetaActiveWindPacifiCorpLBNL
402 MW generation in San Juan, UT · In queue since May 2024 · Proposed COD June 2028
402 MW
Capacity
1
Components
Wind
1y 10m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 1m
Pre-Study0%
Queue EntryMay 8, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-06-01
Project Details
State
UT
County
San Juan
Region
West
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Huntington - Pinto transmission line
Data Source
LBNL
No news available for this project.