1.6 MW generation in Multnomah, OR · In queue since May 2024 · Proposed COD September 2026
1.6 MW
Capacity
1
Components
Solar
1y 10m
In Queue
—
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 4m
Pre-Study0%
Queue EntryMay 6, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-09-01
Project Details
State
OR
County
Multnomah
Region
West
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Circuit 5P478 out of Columbia substation
Data Source
LBNL