— Project Summary

Queue ID
PacifiCorp-C4-010
Capacity
50 MW
Technology
Battery
Status
active
Location
Iron, UT
Region
West
Developer
IA Status

BetaActiveBatteryPacifiCorpLBNL

50 MW storage in Iron, UT · In queue since April 2024 · Proposed COD December 2028

50 MW

Capacity

1

Components

Battery

1y 11m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 8m

Pre-Study0%
Queue EntryApr 29, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-31

Project Details

State

UT

County

Iron

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Parowan Valley substation

Data Source

LBNL

No news available for this project.