— Project Summary

Queue ID
PacifiCorp-C4-009
Capacity
20 MW
Technology
Solar+Battery
Status
active
Location
Umatilla, OR
Region
West
Developer
IA Status

BetaActiveSolarBatteryPacifiCorpLBNL

20 MW hybrid in Umatilla, OR · In queue since April 2024 · Proposed COD December 2027

20 MW

Capacity

1

Components

Solar

1y 11m

In Queue

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 8m

Pre-Study0%
Queue EntryApr 29, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

Project Details

State

OR

County

Umatilla

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Pendleton McNary transmission line

Data Source

LBNL