BetaActiveGeothermalPacifiCorpLBNL
20 MW generation in Millard, UT · In queue since April 2024
20 MW
Capacity
1
Components
Geothermal
1y 11m
In Queue
—
IA Status
Interconnection Timeline
Total Duration
1y 11m
Pre-Study0%
Queue EntryApr 12, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
UT
County
Millard
Region
West
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Fillmore - Flowell transmission line
Data Source
LBNL