— Project Summary

Queue ID
PacifiCorp-C4-001
Capacity
3.6 MW
Technology
Other
Status
active
Location
Beaver, UT
Region
West
Developer
IA Status

BetaActiveGeothermalPacifiCorpLBNL

3.6 MW generation in Beaver, UT · In queue since April 2024 · Proposed COD December 2025

3.6 MW

Capacity

1

Components

Geothermal

1y 11m

In Queue

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

1y 8m

Schedule

3 months past proposed COD

Pre-Study0%
Queue EntryApr 4, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

Project Details

State

UT

County

Beaver

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Circuit SCM11 out of School Mine substation

Data Source

LBNL

No news available for this project.