BetaActiveGeothermalPacifiCorpLBNL
3.6 MW generation in Beaver, UT · In queue since April 2024 · Proposed COD December 2025
3.6 MW
Capacity
1
Components
Geothermal
1y 11m
In Queue
—
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
1y 8m
Schedule
3 months past proposed COD
Pre-Study0%
Queue EntryApr 4, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
UT
County
Beaver
Region
West
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Circuit SCM11 out of School Mine substation
Data Source
LBNL
No news available for this project.