BetaActiveSolarPacifiCorpLBNL
3 MW generation in Crook, OR · In queue since May 2023 · Proposed COD December 2024
3 MW
Capacity
1
Components
Solar
2y 10m
In Queue
Facility Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
1y 7m
Schedule
16 months past proposed COD
Facilities Study50%
Queue EntryMay 15, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-01
Project Details
State
OR
County
Crook
Region
West
Developer
CP Prineville, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Circuit 5D126 out of Prineville substation
Data Source
LBNL