BetaActiveSolarBatteryPacifiCorpLBNL
300 MW hybrid in Tooele, UT · In queue since May 2023 · Proposed COD December 2028
300 MW
Capacity
1
Components
Solar
2y 10m
In Queue
—
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 7m
Pre-Study0%
Queue EntryMay 15, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-29
Project Details
State
UT
County
Tooele
Region
West
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Clover - Limber transmission line
Data Source
LBNL
No news available for this project.