23.5 MW hybrid in Lake, OR · In queue since May 2023 · Proposed COD July 2027
23.5 MW
Capacity
1
Components
Solar
2y 10m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 2m
Pre-Study0%
Queue EntryMay 12, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-07-01
Project Details
State
OR
County
Lake
Region
West
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Bullard substation
Data Source
LBNL