— Project Summary

Queue ID
PacifiCorp-C3-072
Capacity
10 MW
Technology
Solar+Battery
Status
active
Location
Box Elder, UT
Region
West
Developer
IA Status

BetaActiveSolarBatteryPacifiCorpLBNL

10 MW hybrid in Box Elder, UT · In queue since May 2023 · Proposed COD December 2024

10 MW

Capacity

1

Components

Solar

2y 10m

In Queue

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

1y 7m

Schedule

15 months past proposed COD

Pre-Study0%
Queue EntryMay 11, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-31

Project Details

State

UT

County

Box Elder

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Lampo substation

Data Source

LBNL

No news available for this project.