30 MW hybrid in Box Elder, UT · In queue since May 2023 · Proposed COD December 2025
30 MW
Capacity
1
Components
Solar
2y 10m
In Queue
—
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 7m
Schedule
3 months past proposed COD
Pre-Study0%
Queue EntryMay 11, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
UT
County
Box Elder
Region
West
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Lampo substation
Data Source
LBNL