— Project Summary

Queue ID
PacifiCorp-C3-056
Capacity
199 MW
Technology
Solar+Battery
Status
active
Location
Utah, UT
Region
West
Developer
IA Status

BetaActiveSolarBatteryPacifiCorpLBNL

199 MW hybrid in Utah, UT · In queue since May 2023 · Proposed COD December 2027

199 MW

Capacity

1

Components

Solar

2y 10m

In Queue

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 7m

Pre-Study0%
Queue EntryMay 10, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

Project Details

State

UT

County

Utah

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Mercer substation

Data Source

LBNL

No news available for this project.