200 MW storage in Franklin, ID · In queue since May 2023 · Proposed COD January 2030
200 MW
Capacity
1
Components
Other Storage
2y 10m
In Queue
—
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
6y 8m
Pre-Study0%
Queue EntryMay 10, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-01-04
Project Details
State
ID
County
Franklin
Region
West
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Oneida substation
Data Source
LBNL