BetaActiveSolarBatteryPacifiCorpLBNL
500 MW hybrid in Millard, UT · In queue since May 2023 · Proposed COD January 2027
500 MW
Capacity
1
Components
Solar
2y 10m
In Queue
—
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 8m
Pre-Study0%
Queue EntryMay 8, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-01-07
Project Details
State
UT
County
Millard
Region
West
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Pavant substation
Data Source
LBNL
No news available for this project.