— Project Summary

Queue ID
PacifiCorp-C3-027
Capacity
275 MW
Technology
Solar+Battery
Status
active
Location
Juab, UT
Region
West
Developer
IA Status

BetaActiveSolarBatteryPacifiCorpLBNL

275 MW hybrid in Juab, UT · In queue since May 2023 · Proposed COD December 2026

275 MW

Capacity

1

Components

Solar

2y 10m

In Queue

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 7m

Pre-Study0%
Queue EntryMay 4, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

UT

County

Juab

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Mona substation

Data Source

LBNL

No news available for this project.