— Project Summary

Queue ID
PacifiCorp-C3-022
Capacity
300 MW
Technology
Wind+Battery
Status
active
Location
Sweetwater, WY
Region
West
Developer
IA Status

BetaActiveWindBatteryPacifiCorpLBNL

300 MW hybrid in Sweetwater, WY · In queue since May 2023 · Proposed COD December 2027

300 MW

Capacity

1

Components

Wind

2y 10m

In Queue

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 7m

Pre-Study0%
Queue EntryMay 2, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

Project Details

State

WY

County

Sweetwater

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Anticline substation

Data Source

LBNL

No news available for this project.