500 MW generation in Sweetwater, WY · In queue since April 2023 · Proposed COD December 2025
500 MW
Capacity
1
Components
Wind
2y 11m
In Queue
—
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 8m
Schedule
3 months past proposed COD
Pre-Study0%
Queue EntryApr 28, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
WY
County
Sweetwater
Region
West
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Anticline substation
Data Source
LBNL