— Project Summary

Queue ID
PacifiCorp-C3-011
Capacity
199.9 MW
Technology
Battery
Status
active
Location
Lake, OR
Region
West
Developer
PacifiCorp
IA Status

BetaActiveBatteryPacifiCorpLBNL

199.9 MW storage in Lake, OR · In queue since April 2023 · Proposed COD December 2029

199.9 MW

Capacity

1

Components

Battery

2y 11m

In Queue

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

6y 8m

Pre-Study0%
Queue EntryApr 7, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-12-31

Project Details

State

OR

County

Lake

Region

West

Developer

PacifiCorp

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Summer Lake substation

Data Source

LBNL