— Project Summary

Queue ID
PacifiCorp-C2-99
Capacity
166 MW
Technology
Solar+Battery
Status
active
Location
Emery, UT
Region
West
Developer
IA Status
Facility Study

BetaActiveSolarBatteryPacifiCorpLBNL

166 MW hybrid in Emery, UT · In queue since May 2022 · Proposed COD December 2026

166 MW

Capacity

1

Components

Solar

3y 10m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 7m

Facilities Study50%
Queue EntryMay 13, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

UT

County

Emery

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Emery substation

Data Source

LBNL

No news available for this project.