BetaActiveSolarBatteryPacifiCorpLBNL
300 MW hybrid in Bannock, ID · In queue since May 2022 · Proposed COD December 2027
300 MW
Capacity
1
Components
Solar
3y 10m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 7m
Construction75%
Queue EntryMay 12, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2027-12-31
Project Details
State
ID
County
Bannock
Region
West
Developer
BRP Garnet 1, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Populus substation
Data Source
LBNL
No news available for this project.