— Project Summary

Queue ID
PacifiCorp-C2-82
Capacity
300 MW
Technology
Solar+Battery
Status
active
Location
Bannock, ID
Region
West
Developer
BRP Garnet 1, LLC
IA Status
IA Executed

BetaActiveSolarBatteryPacifiCorpLBNL

300 MW hybrid in Bannock, ID · In queue since May 2022 · Proposed COD December 2027

300 MW

Capacity

1

Components

Solar

3y 10m

In Queue

IA Executed

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5y 7m

Construction75%
Queue EntryMay 12, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2027-12-31

Project Details

State

ID

County

Bannock

Region

West

Developer

BRP Garnet 1, LLC

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Populus substation

Data Source

LBNL

No news available for this project.