— Project Summary

Queue ID
PacifiCorp-C2-79
Capacity
145 MW
Technology
Battery
Status
active
Location
Linn, OR
Region
West
Developer
IA Status
Facility Study

BetaActiveBatteryPacifiCorpLBNL

145 MW storage in Linn, OR · In queue since May 2022 · Proposed COD December 2025

145 MW

Capacity

1

Components

Battery

3y 10m

In Queue

Facility Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 7m

Schedule

3 months past proposed COD

Facilities Study50%
Queue EntryMay 11, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

Project Details

State

OR

County

Linn

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Conser Road-Murder Creek transmission line

Data Source

LBNL

No news available for this project.