BetaActiveBatteryPacifiCorpLBNL
145 MW storage in Linn, OR · In queue since May 2022 · Proposed COD December 2025
145 MW
Capacity
1
Components
Battery
3y 10m
In Queue
Facility Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 7m
Schedule
3 months past proposed COD
Facilities Study50%
Queue EntryMay 11, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
OR
County
Linn
Region
West
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Conser Road-Murder Creek transmission line
Data Source
LBNL
No news available for this project.