500 MW generation in Lincoln, WY · In queue since April 2022 · Proposed COD November 2030
500 MW
Capacity
1
Components
Nuclear
3y 11m
In Queue
—
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
8y 7m
Pre-Study0%
Queue EntryApr 26, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-11-01
Project Details
State
WY
County
Lincoln
Region
West
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Naughton substation
Data Source
LBNL