100 MW storage in Multnomah, OR · In queue since April 2022 · Proposed COD July 2024
100 MW
Capacity
1
Components
Battery
3y 11m
In Queue
IA Executed
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 3m
Schedule
21 months past proposed COD
Construction75%
Queue EntryApr 18, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2024-07-01
Project Details
State
OR
County
Multnomah
Region
West
Developer
Troutdale Grid, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Troutdale substation
Data Source
LBNL