BetaActiveBatteryPacifiCorpLBNL
20 MW storage in Uintah, UT · In queue since May 2022 · Proposed COD October 2025
20 MW
Capacity
1
Components
Battery
3y 10m
In Queue
IA Executed
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 5m
Schedule
6 months past proposed COD
Construction75%
Queue EntryMay 15, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2025-10-01
Project Details
State
UT
County
Uintah
Region
West
Developer
Revolve Vernal BESS, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Ashley substation
Data Source
LBNL
No news available for this project.