— Project Summary

Queue ID
PacifiCorp-C2-209
Capacity
20 MW
Technology
Battery
Status
active
Location
Uintah, UT
Region
West
Developer
Revolve Vernal BESS, LLC
IA Status
IA Executed

BetaActiveBatteryPacifiCorpLBNL

20 MW storage in Uintah, UT · In queue since May 2022 · Proposed COD October 2025

20 MW

Capacity

1

Components

Battery

3y 10m

In Queue

IA Executed

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 5m

Schedule

6 months past proposed COD

Construction75%
Queue EntryMay 15, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2025-10-01

Project Details

State

UT

County

Uintah

Region

West

Developer

Revolve Vernal BESS, LLC

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Ashley substation

Data Source

LBNL

No news available for this project.