BetaActiveGeothermalPacifiCorpLBNL
40 MW generation in Millard, UT · In queue since May 2022 · Proposed COD December 2029
40 MW
Capacity
1
Components
Geothermal
3y 10m
In Queue
Suspended
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
7y 7m
In Study38%
Queue EntryMay 15, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-12-31
Project Details
State
UT
County
Millard
Region
West
Developer
FEC Development LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Black Rock substation
Data Source
LBNL
No news available for this project.