— Project Summary

Queue ID
PacifiCorp-C2-167
Capacity
125 MW
Technology
Solar
Status
active
Location
Emery, UT
Region
West
Developer
PacifiCorp
IA Status
Facility Study

BetaActiveSolarPacifiCorpLBNL

125 MW generation in Emery, UT · In queue since May 2022 · Proposed COD May 2026

125 MW

Capacity

1

Components

Solar

3y 10m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4 years

Facilities Study50%
Queue EntryMay 15, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-05-01

Project Details

State

UT

County

Emery

Region

West

Developer

PacifiCorp

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Huntington-Pinto transmission line

Data Source

LBNL