BetaActiveSolarBatteryPacifiCorpLBNL
86 MW hybrid in Yakima, WA · In queue since May 2022 · Proposed COD November 2024
86 MW
Capacity
1
Components
Solar
3y 10m
In Queue
—
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 6m
Schedule
16 months past proposed COD
Pre-Study0%
Queue EntryMay 15, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-11-30
Project Details
State
WA
County
Yakima
Region
West
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Tieton substation
Data Source
LBNL
No news available for this project.