— Project Summary

Queue ID
PacifiCorp-C2-152
Capacity
320 MW
Technology
Solar+Battery
Status
active
Location
Lake, OR
Region
West
Developer
IA Status
Facility Study

BetaActiveSolarBatteryPacifiCorpLBNL

320 MW hybrid in Lake, OR · In queue since May 2022 · Proposed COD May 2028

320 MW

Capacity

1

Components

Solar

3y 10m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

6 years

Facilities Study50%
Queue EntryMay 15, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-05-15

Project Details

State

OR

County

Lake

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Burns-Summer Lake transmission line

Data Source

LBNL

No news available for this project.