— Project Summary

Queue ID
PacifiCorp-C2-112
Capacity
199 MW
Technology
Solar+Battery
Status
active
Location
Utah, UT
Region
West
Developer
IA Status

BetaActiveSolarBatteryPacifiCorpLBNL

199 MW hybrid in Utah, UT · In queue since May 2022 · Proposed COD December 2025

199 MW

Capacity

1

Components

Solar

3y 10m

In Queue

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 7m

Schedule

3 months past proposed COD

Pre-Study0%
Queue EntryMay 13, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-21

Project Details

State

UT

County

Utah

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Mercer substation

Data Source

LBNL