— Project Summary

Queue ID
PacifiCorp-C2-110
Capacity
199 MW
Technology
Battery
Status
active
Location
Utah, UT
Region
West
Developer
IA Status

BetaActiveBatteryPacifiCorpLBNL

199 MW storage in Utah, UT · In queue since May 2022 · Proposed COD December 2025

199 MW

Capacity

1

Components

Battery

3y 10m

In Queue

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 7m

Schedule

3 months past proposed COD

Pre-Study0%
Queue EntryMay 13, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

Project Details

State

UT

County

Utah

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Mercer substation

Data Source

LBNL

No news available for this project.