BetaActiveOther StoragePacifiCorpLBNL
500 MW storage in Salt Lake, UT · In queue since April 2022 · Proposed COD December 2027
500 MW
Capacity
1
Components
Other Storage
3y 11m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 8m
Construction75%
Queue EntryApr 5, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2027-12-31
Project Details
State
UT
County
Salt Lake
Region
West
Developer
Oquirrh Energy Storage, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Oquirrh substation
Data Source
LBNL
No news available for this project.