— Project Summary

Queue ID
PacifiCorp-C2-09
Capacity
80 MW
Technology
Solar+Battery
Status
active
Location
Crook, OR
Region
West
Developer
IA Status

BetaActiveSolarBatteryPacifiCorpLBNL

80 MW hybrid in Crook, OR · In queue since April 2022 · Proposed COD May 2026

80 MW

Capacity

1

Components

Solar

3y 11m

In Queue

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 1m

Pre-Study0%
Queue EntryApr 1, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-05-30

Project Details

State

OR

County

Crook

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Ponderosa substation

Data Source

LBNL

No news available for this project.