— Project Summary

Queue ID
PacifiCorp-C1-58
Capacity
2 MW
Technology
Wind
Status
active
Location
Salt Lake, UT
Region
West
Developer
IA Status
Facility Study

BetaActiveWindPacifiCorpLBNL

2 MW generation in Salt Lake, UT · In queue since May 2021 · Proposed COD January 2023

2 MW

Capacity

1

Components

Wind

4y 10m

In Queue

Facility Study

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

1y 8m

Schedule

38 months past proposed COD

Facilities Study50%
Queue EntryMay 14, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-01-31

Project Details

State

UT

County

Salt Lake

Region

West

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Circuit RKW17 out of Porter Rockwell substation

Data Source

LBNL

No news available for this project.