BetaActiveWindPacifiCorpLBNL
2 MW generation in Salt Lake, UT · In queue since May 2021 · Proposed COD January 2023
2 MW
Capacity
1
Components
Wind
4y 10m
In Queue
Facility Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
1y 8m
Schedule
38 months past proposed COD
Facilities Study50%
Queue EntryMay 14, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-01-31
Project Details
State
UT
County
Salt Lake
Region
West
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Circuit RKW17 out of Porter Rockwell substation
Data Source
LBNL
No news available for this project.