BetaActiveSolarBatteryPacifiCorpLBNL
199 MW hybrid in Utah, UT · In queue since May 2021 · Proposed COD October 2024
199 MW
Capacity
1
Components
Solar
4y 10m
In Queue
IA Executed
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 5m
Schedule
17 months past proposed COD
Construction75%
Queue EntryMay 14, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2024-10-31
Project Details
State
UT
County
Utah
Region
West
Developer
Pinyon Creek Solar LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Mercer-Mona #1 transmission line
Data Source
LBNL
No news available for this project.