BetaSuspendedSolarBatteryPacifiCorpLBNL
300 MW hybrid in Juab, UT · In queue since May 2021 · Proposed COD October 2024
300 MW
Capacity
1
Components
Solar
4y 10m
In Queue
Suspended
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 5m
Suspended38%
Queue EntryMay 14, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-10-01
Project Details
State
UT
County
Juab
Region
West
Developer
Thirsty Valley Solar Energy LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Clover substation
Data Source
LBNL
No news available for this project.