— Project Summary

Queue ID
PacifiCorp-C1-51
Capacity
300 MW
Technology
Solar+Battery
Status
suspended
Location
Juab, UT
Region
West
Developer
Thirsty Valley Solar Energy LLC
IA Status
Suspended

BetaSuspendedSolarBatteryPacifiCorpLBNL

300 MW hybrid in Juab, UT · In queue since May 2021 · Proposed COD October 2024

300 MW

Capacity

1

Components

Solar

4y 10m

In Queue

Suspended

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 5m

Suspended38%
Queue EntryMay 14, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-10-01

Project Details

State

UT

County

Juab

Region

West

Developer

Thirsty Valley Solar Energy LLC

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Clover substation

Data Source

LBNL