BetaSuspendedSolarBatteryPacifiCorpLBNL
400 MW hybrid in Utah, UT · In queue since May 2021 · Proposed COD December 2024
400 MW
Capacity
1
Components
Solar
4y 10m
In Queue
Suspended
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 7m
Suspended38%
Queue EntryMay 14, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-15
Project Details
State
UT
County
Utah
Region
West
Developer
Mosida Solar, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Mercer-Mona #1 transmission line
Data Source
LBNL
No news available for this project.