BetaSuspendedSolarBatteryPacifiCorpLBNL
400 MW hybrid in Lake, OR · In queue since May 2021 · Proposed COD October 2025
400 MW
Capacity
1
Components
Solar
4y 10m
In Queue
Suspended
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
4y 5m
Suspended38%
Queue EntryMay 14, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-10-01
Project Details
State
OR
County
Lake
Region
West
Developer
Archway Solar Energy LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Burns-Summer Lake transmission line
Data Source
LBNL