BetaActiveSolarBatteryPacifiCorpLBNL
300 MW hybrid in Washington, UT · In queue since May 2021 · Proposed COD June 2023
300 MW
Capacity
1
Components
Solar
4y 10m
In Queue
IA Executed
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 1m
Schedule
34 months past proposed COD
Construction75%
Queue EntryMay 14, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2023-06-15
Project Details
State
UT
County
Washington
Region
West
Developer
REBU BN, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Red Butte Three Peaks Sigurd transmission line
Data Source
LBNL
No news available for this project.