500 MW generation in Carbon, WY · In queue since May 2021 · Proposed COD December 2024
500 MW
Capacity
1
Components
Wind
4y 10m
In Queue
IA Executed
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 7m
Schedule
15 months past proposed COD
Construction75%
Queue EntryMay 13, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2024-12-31
Project Details
State
WY
County
Carbon
Region
West
Developer
Lucky Star Wind, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Point of Interconnection
Aeolus substation
Data Source
LBNL
No news available for this project.