— Project Summary

Queue ID
PacifiCorp-C1-34
Capacity
200 MW
Technology
Solar+Battery
Status
active
Location
Utah, UT
Region
West
Developer
Quicksilver Solar, LLC
IA Status
IA Executed

BetaActiveSolarBatteryPacifiCorpLBNL

200 MW hybrid in Utah, UT · In queue since May 2021 · Proposed COD December 2024

200 MW

Capacity

1

Components

Solar

4y 10m

In Queue

IA Executed

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 7m

Schedule

15 months past proposed COD

Construction75%
Queue EntryMay 12, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2024-12-31

Project Details

State

UT

County

Utah

Region

West

Developer

Quicksilver Solar, LLC

Utility

PacifiCorp

Entity

PacifiCorp

Point of Interconnection

Mercer substation

Data Source

LBNL

No news available for this project.